Concerns for HGVs at Letterkenny’s Hospital Roundabout in active travel layout

Concerns raised at Letterkenny Milford MD for the Hospital Roundaboutplaceholder image
Concerns raised at Letterkenny Milford MD for the Hospital Roundabout

Cllr Donal Kelly says HGV operators have contacted him regarding road size issues

Buses and lorries could be forced to cross lanes when turning at Letterkenny’s Hospital Roundabout under the new active travel layout, the council has heard.

Cllr Donal Kelly says HGV operators have contacted him about the width of the lane when travelling from Glencar's Circular Road to turn up the Kilmacrennan Road.

"For the life of them, they don’t know how they are going to turn up Mountain Top without crossing lanes,” Cllr Kelly said.

He told the May Letterkenny-Milford Municipal District meeting that he's getting calls every day about the layout.

“It’s important that we get it ironed out," he warned.

Mayor Ciaran Brogan said he was also receiving “an awful lot of calls” about the issue.

The matter is set to be discussed at an upcoming meeting this week.

Senior Roads Engineer David McIlwaine confirmed that the active works are being constructed in accordance with the design, but added that traffic management arrangements may be making the area look tighter at present.

Works on the Kilmacrennan Active Travel Project are due to be completed in July 2026.

The scheme involves narrowing the existing carriageway to two 3m lanes, with a separation zone in the centre of the road and an emergency overrun area.

The latest council update said works have progressed at the north-west quadrant of the Hospital Roundabout, with kerbing and stone sub-base installed for the new footpath and cycle track up and around Glencar Road to the R229 Kilmacrennan Road northbound.

Works have also progressed at the Errigal College bus set-down area, where the finished footpath and bitumen base have been completed north of the existing entrance.

The contractor, ACS Civils Ltd, has moved barriers back behind the new kerb line to restore the bus set-down north of the entrance, allowing students to get off buses onto a concrete pathway.

No red surfacing of cycle tracks has yet commenced.

Councillors were told that traffic management will remain in place and may change as the works continue.

Over the next month, works are expected to include public lighting ducts, base surfacing for cycle tracks, pedestrian crossing facilities and the installation of public lighting.