Contracts signed for new Malin social housing project


The construction of the nine new homes is expected to be completed in July 2026
Donegal County Council recently completed the contract for the design and build of nine new social houses in Malin.
Moneydarragh Construction Ltd will undertake the construction of the nine new homes in the fourth phase of the Radharc na Trá Breige housing estate in Malin town. The expected completion date is July 2026.
The council says the development will provide high-quality, sustainable homes for nine families in the extended Malin area.
Some 37 homes were built during the three previous phases of development at Radharc na Trá Breige, and last year the council said it needed 11 homes for tenants on its housing list in the Malin area.
The application for the nine homes was first submitted in October 2023 and permission was approved under Part VIII of the planning act by county councillors in January 2024.
The nine two-storey homes will vary in size and be built across three blocks. Two of the homes will have two bedrooms, there will also be six three bedroom homes and one four bedroom home.
In its planning application, the council said that no new road entrances are required and the new homes will be accessed through the existing roads servicing the Radharc na Trá Breige development.
Separately, the council also plans to provide two new social homes through the conversion of the former Garda station and adjoining residence in Malin Town. The Part VIII approval was rubber-stamped by councillors in September 2024, with the Department of Housing approving funding in February.