Burnfoot flood relief scheme delayed again with 2029 the new completion date


With planning application not yet submitted, the €13.6m scheme to protect 49 homes won’t be operational for another three years
Burnfoot’s multimillion-euro flood relief scheme has slipped further behind schedule, with RPS, the consultancy engaged by Donegal County Council to design the project, now estimating a completion date of 2029.
The final drawings and compulsory purchase order documents are complete and have been subject to independent legal review. However, Donegal County Council and the Office of Public Works must complete their internal approval processes before a planning application can be made to An Coimisiún Pleanála.
Government funding for new Burnfoot flood defences was announced in the summer of 2018, a year after the village was devastated in the Night of the Big Flood in August 2017.
When the scheme was first announced in November 2020, it was projected to be completed and operational by autumn 2025. However, a planning application has yet to be submitted. Subject to approval, RPS estimates construction will commence in 2028, with the scheme becoming operational in the second quarter of 2029.
The OPW has put a €13.6 million price tag on the overall Burnfoot flood defence scheme, which will protect 49 properties in the village. It is designed to protect against a one-in-200-year flooding event and will consist of 400 metres of concrete flood walls and 890 metres of earthen embankments, averaging 1.1 metres (3.5 feet) in height.
As part of climate change adaptations, deeper foundations are being installed so that the height and extent of the defences can be increased in future if required.
A new single-span bridge on the R238 Buncrana-Derry road will replace the existing structure, providing greater clearance for floodwaters. The bridge replacement on that busy road will require a major traffic management operation, including the construction of a temporary bridge across to carry vehicles.
Sections of the Burnfoot River’s historical floodplain will be re-established downstream of the bridge through the removal of some embankments and the construction of others. The Lios na Gréine estate, where eight social houses remain boarded up since the 2017 floods, will be safeguarded by a sheet-piled wall, while low earthen embankments will protect the Monreagh estate. The culverts carrying the Carnashannagh Stream under the Brae Road will also be upgraded.
Buncrana flood relief
Meanwhile, the Buncrana flood relief remains in the very early pre-planning stages.
Hydraulic modelling has been updated and further ecological surveys are to be carried out this year. Affected landowners will be contacted in advance to discuss the proposed investigation works and to arrange access.
Individual flood cells have been identified, each representing an area that can be protected independently of others.