Buncrana three-school campus stalled by further information request

3D Visuals of the proposed school campus by Kennedy Fitzgerald Architectsplaceholder image
3D Visuals of the proposed school campus by Kennedy Fitzgerald Architects

Planners have identified several key concerns that must be addressed before a decision can be made, pushing the timeline for the project further back.

Plans for the long-awaited Buncrana Three-School Campus have been delayed by at least a further six months after Donegal County Council issued a comprehensive request for additional information on the project.

The application, submitted in early March by the Donegal Education and Training Board on behalf of the Department of Education, relates to the proposed development of a shared secondary school for Crana College and Coláiste Eoghain, alongside a new primary school for Gaelscoil Bhun Cranncha on the Causeway Road.

However, planners have identified several key concerns that must be addressed before a decision can be made, pushing the timeline for the project further back.

Among the most significant issues raised are traffic and road safety concerns. The Council has called for a revised junction design at the already busy junction of Causeway Road and Cockhill Road. 

The original plans included a signalised T-junction with traffic lights to accommodate increased traffic levels, but further detail is now required. 

This includes consideration of relocating the junction, introducing controlled pedestrian and cyclist crossings, and assessing the need for road widening, which could result in the school campus being set back slightly around its perimeter, along with extended turning lanes to handle school transport and peak-time congestion.

In addition, the applicant has been asked to provide detailed traffic modelling and vehicle tracking analysis to demonstrate that buses and other vehicles can safely navigate the site without causing queuing onto surrounding roads.

A shortfall in parking capacity is one area the planning authority is seeking to address before they make a decision. While 101 spaces are proposed, only 78 are standard parking spaces, despite an estimated staffing level of approximately 94 across the three schools. 

Council officials have requested a revised parking assessment, including provision for staff, visitors, and potential student demand, as well as measures to prevent overspill parking in nearby residential areas.

Active travel infrastructure has emerged as another key issue. The Council has requested clarification and amendment of all drawings to confirm that pedestrian and cycling infrastructure, both within the site and along adjoining roads, will be delivered by the developer, not the local authority. Concerns were raised that elements of the current plans incorrectly assign responsibility to Donegal County Council.

Further information has also been sought regarding integration with the proposed  Buncrana to Carndonagh greenway, as well as safe pedestrian and cyclist access at the boundary of the site and nearby junctions.

Infrastructure capacity remains uncertain, with Uisce Éireann indicating that insufficient information has been provided to confirm the adequacy of water supply and wastewater services. The applicant must now submit additional technical details, including the outcome of a Pre-Connection Enquiry and any required upgrades.

Drainage and flood risk are also under scrutiny, particularly in relation to the adjoining road. The Council has requested detailed surface water design, downstream capacity confirmation, and further modelling to ensure the development will not increase flood risk or lead to flooding on-site.

The planning authority has set a deadline of October 30 for the submission of the requested information, after which a final decision will be made.

Reacting to the latest setback, South Inishowen Councillor Jack Murray described the delay as “deeply disappointing,” noting the project has already faced decades of delays and missed opportunities.

“As a member of Crana College Board of Management, I know how disappointing this will be. I have seen first-hand the vigour, passion and commitment that the school community has put into this project, as have those in Gaelscoil Bun Cranncha and Coláiste Eoghain.”

The Sinn Féin Councillor stressed that “proper planning matters’ and nobody wants corners cut."

“But a project of this scale and importance should have been prepared to the highest possible standard before it ever reached this stage,” he added.

“Every possible query should have been anticipated, including traffic, access, active travel, and how pupils can safely get to and from the new campus.”

“That is particularly frustrating after the last delay, when it appeared that the need for an active travel plan had not been fully anticipated. This speaks to a wider culture of delays at government level.”

“Locally, we have seen repeated delays to Buncrana Leisure Centre, Buncrana Nursing Unit, Burnfoot flood defences, and now the Three School Campus again.”

Councillor Murray also said, "Government Ministers must meet us halfway. They must ensure that departments, design teams, and agencies are properly overseeing these projects, anticipating problems early, and driving them forward with urgency.”

No timelines have been provided for the construction of the school buildings; however, based on the Department’s five-stage process for major building projects, it will be 2030 before the first students will actually be taught there, though that now appears increasingly uncertain.