Planning permission granted for major dredging machine facility in Greencastle

Dredging at Greencastle breakwater last yearplaceholder image
Dredging at Greencastle breakwater last year | Iconic

Major new marine facility approved for Greencastle with strict conditions on operating hours, noise and drainage

Planning permission has been granted for a large storage, repair and maintenance facility for dredging machinery in Greencastle.

Foyle Marine Contractors has received approval from Donegal County Council for the construction of a 1,700 square metre (approximately 18,000 sq ft) building which will also include offices and ancillary accommodation at Drumaweer, close to Greencastle Harbour.

Retention permission was also granted for excavation works which had already commenced on the Greencastle site.

The development will also include an on-site 22,000-litre effluent storage tank, along with associated site works.

Donegal County Council granted permission subject to 12 conditions. Under the conditions, operating hours at the facility will be restricted to between 8am and 7pm Monday to Friday and 8am to 4pm on Saturdays. The facility will not be permitted to operate on Sundays or public holidays unless otherwise agreed with the planning authority.

The council has also imposed noise limits on the development. Noise levels at the nearest noise-sensitive locations, including residential properties, must not exceed 55 decibels during daytime operating hours and 45 decibels at other times. Night-time noise emissions must also have no tonal component.

The permission states that no surface water from the site can discharge onto the public road, while measures must be taken to prevent water from the public road entering the site.

Restrictions have also been placed on construction hours. Building and site development works will generally be permitted between 7am and 6pm Monday to Friday and 8am to 2pm on Saturdays, with no works permitted on Sundays or public holidays unless exceptional circumstances arise and prior written approval is obtained from the planning authority.

A detailed Construction Management Plan must also be agreed with Donegal County Council before the development begins.

The plan will cover a range of issues including construction traffic, site security, parking for workers, storage of materials and construction waste, abnormal-load deliveries, noise, dust and vibration control, and measures to prevent debris being deposited on public roads.

It must also include measures to prevent fuel and oil spillages, manage excavated soil and ensure that surface water runoff does not carry silt or pollutants into local drains or surface water systems.

The planning authority has further required the applicant to enter into an agreement with a licensed wastewater contractor for the removal and disposal of wastewater from the site.

The development must also comply with the recommendations and mitigation measures contained in the submitted Flood Risk Assessment and associated drainage proposals.

All flood mitigation measures must be implemented before the facility is occupied or brought into use and must be maintained for the lifetime of the development.